Snow Melting System A Sure Bet For Casino

The casino project involves parking areas, bridges, pedestrian walkways, and a main plaza covered in cobblestone.
NIAGARA FALLS, Ontario — The mist from the world-famous Horseshoe Falls in Niagara Falls is a beautiful sight to behold. But during the winter months in this Ontario city, the mist can spell danger, too. That’s because sometimes the mist immediately forms sheets of ice on the area sidewalks and streets, which can lead to mayhem for drivers and pedestrians.

So when the new Niagara Falls Casino/Gateway Project was in the planning stages, the architects were keenly aware of liability issues if casino patrons failed to negotiate the icy surfaces.

“Horseshoe Falls gives off a fine mist, even in the wintertime,” said Sal Fiorillo of Sayers and Associates, the mechanical contractor for the casino project. “It could be very perilous for the people coming in and out of the casino and also for the parking ramps and bus waiting areas during the winter months.” Sayers and Associates is installing all of the plumbing, piping, sheet metal work, and heating and cooling equipment for the project, including the Rehau snow and ice melt (SIM) system.

“The real clincher was when the architect drove up and spun out at the construction site,” quipped Mark Euteneier, technical associate for Klimatrol Environmental Systems Ltd., the company that is supplying parts and piping for the SIM system. The SIM system consists of RAUPEX pipe, Everloc® fittings, industrial manifolds, and modern controls.

The approximately 125,000-square-foot system will be installed in parking lot areas and walkways to melt the accumulation of snow and ice. The system is designed to clear snow and ice from vehicle and pedestrian pathways quickly and efficiently.

Euteneir said the casino project provided a unique challenge because of the many bridges, suspended parking ramps, and the main plaza covered in cobblestone. But he said it was important that all surfaces be kept ice-free, regardless of the challenge.

“There are a lot of insurance liabilities involved,” he said. “We have worked on projects like hospitals and public buildings where public safety has been important.”

Workers carefully install part of the 125,000-square-foot snow and ice melting system for the Niagara Falls Casino/Gateway Project.

The System

The pipe is designed to provide extended system life and optimum performance under rugged conditions. It is designed to maintain its structural integrity even after repeated bending during installation and resist conventional solvents and chemicals, as well as hydrous salt and acid solutions.

The system melts snow and ice when heated fluid is circulated throughout the pipe, which is installed underneath or within an outdoor ground surface. The SIM system facilitates snow removal, minimizing the need to apply salt or other melting agents that can corrode many surfaces. Indoor maintenance costs can also be reduced because less salt and water is tracked inside buildings.

“Snow and ice melting systems are becoming more common in Canada because of winter conditions where wide and sloped areas need to be clear all year round,” said Fiorillo. “Rehau was selected for this project because of the reliability and credibility of its product.”

The Niagara Falls Casino/Gateway Project, which began construction in October 2001, is expected to cost $800 million. Situated on an eight-hectare site overlooking Horseshoe Falls, the complex will house a 100,000-square-foot casino with 3,000 slot machines, 150 gaming tables, a 368-room hotel, 50,000 square feet of meeting and exhibit space, and a 1,500-seat performing arts center.

For more information, visit www.rehau-na.com and www.klimatrol.com.

Publication date: 10/13/2003

Did you enjoy this article? Click here to subscribe to The NEWS Magazine

John Hall is the Business Editor. E-mail him at johnhall@achrnews.com.

Recent Articles by John Hall

You must login or register in order to post a comment.

Multimedia

Videos

Image Galleries

2013 ACCA Conference & IE3 Expo

Photos from the 2013 ACCA Conference & IE3 Expo in Orlando, Fla.

Podcasts

Cade Clark, assistant vice president of government affairs for the Air-Conditioning, Heating & Refrigeration Institute (AHRI), gives a brief overview of the new version of the Shaheen-Portman bill, what AHRI thinks of the energy-efficiency legislation, and how it might affect the HVACR industry if it becomes law.
More Podcasts

THE MAGAZINE

ACHRNEWS

NEWS 05-20-13 cover

2013 May 20

Check out the weekly edition of The NEWS today!

Table Of Contents Subscribe

HVAC LEASING

Some HVAC contractors have introduced leasing programs for consumers. Do you think this is a viable option?
View Results Poll Archive

Clear Seas Research

Clear Seas ResearchWith access to over one million professionals and more than 60 industry-specific publications, Clear Seas Research offers relevant insights from those who know your industry best. Let us customize a market research solution that exceeds your marketing goals.

DON'T MISS A THING

Magazine image
 
Register today for complete access to ACHRNews.com. Get full access to the latest features, Extra Edition, and more.

STAY CONNECTED

facebook icontwitter iconyoutube iconLinkedIn i con