Power plants are usually fairly self-sufficient when it comes to their own repair work. But violent weather caused damages that made one facility (which shall remain nameless in this article) look outside for help.

A June 1999 tornado damaged a 115,000-gpm cooling tower at this plant in the Midwest — one of the six main cooling towers at the plant — completely destroying the unit.

A local cooling tower company was contacted to repair and rebuild the towers. This company, in turn, contacted Aggreko Industrial Cooling Towers to provide temporary cooling towers for use during the rebuilding effort.

Aggreko met with the cooling tower company the next day and immediately shipped the units, replacing the original unit with 46 1,000-ton modular cooling towers.

In addition, the company provided two 2,500-kVA transformers, electrical distribution equipment, and a complete piping system. The units brought the plant’s power generation back to maximum capacity in eight days, and remained on-site through September.

“The size of the project basically eliminated everyone else from the pool of eligible companies,” said Billy Childers, Aggreko Industrial Cooling Tower Center national manager.

“We had the project team and the equipment necessary to support the project.”

The company’s modular cooling tower design allowed the equipment to be placed in the limited space. The design also features an elevated cold-water basin, which eliminates the need for additional pumps.

“We decided to utilize the modular design as opposed to a mounted unit because it saves space, enables better water flow, and allows the user to combine as many units as necessary,” Childers explained.

The power company was able to save an enormous amount in electricity costs each day. The electricity would have cost the company hundreds of thousands of dollars per day — literally millions during the duration of the project.

Did you enjoy this article? Click here to subscribe to The NEWS Magazine

You must login or register in order to post a comment.

Multimedia

Videos

Image Galleries

2014 MCAA Annual Convention

Scenes from the 2014 MCAA Annual Convention in Scottsdale, Ariz.

Podcasts

Kyle Gargaro, editor-in-chief of The NEWS, hosted the 2014 ACCA CEO Forum. At the event, six well-known, highly respected company executives, Gary Michel, Ingersoll Rand/Trane; Chris Nelson, Carrier Corp.; Chris Peel, Rheem Mfg. Co.; Rod Rushing, Johnson Controls; Brent Schroeder, Emerson Climate Technologies; and Doug Young, Lennox; provided individual industry outlooks and fielded questions directly from attending contractors. Listen to the entire event on the NEWSMakers podcast. Posted on April 14.

More Podcasts

THE MAGAZINE

ACHRNEWS

NEWS 04-14-14 cover

2014 April 14

Check out the weekly edition of The NEWS today!

Table Of Contents Subscribe

SERVICE CALLS POLL

Which statement on service calls best applies to your business?
View Results Poll Archive

HVACR INDUSTRY STORE

plumbing-hvac.gif
2014 National Plumbing & HVAC Estimator

Every plumbing and HVAC estimator can use the cost estimates in this practical manual!

More Products

Clear Seas Research

 

Clear Seas ResearchWith access to over one million professionals and more than 60 industry-specific publications, Clear Seas Research offers relevant insights from those who know your industry best. Let us customize a market research solution that exceeds your marketing goals.

DON'T MISS A THING

Magazine image
 
Register today for complete access to ACHRNews.com. Get full access to the latest features, Extra Edition, and more.

STAY CONNECTED

facebook icontwitter iconyoutube iconLinkedIn i con