Last month we examined the operation and application of the potential starting relay. This month we will cover voltage specifications of the potential relay.

Compressors may have one of three voltage rating specifications. Service technicians need to know that potential relays must be sized to each individual compressor.

All potential relays have voltage ratings or voltage specifications. An example of a potential relay specification is shown in Figure 1.

Pickup voltage: The pickup voltage is the back EMF (electromagnetic field) voltage generated across the start winding by the motor’s rotor when it is up to about three-quarters speed.

The pickup voltage for a specified potential relay is listed as a minimum and a maximum. The actual pickup voltage must stay within this range for proper operation. If the pickup voltage generated by back EMF is under the minimum, the contacts between terminals 1 and 2 will never open. The start capacitor will then stay in the circuit. This will cause high amp draw and the motor’s protective devices will open.

If the pickup voltage generated by back EMF is above the maximum, the relay coil stands a good chance to overheat and open circuit. Again, the contacts between 1 and 2 would stay closed, causing high amp draw if the relay coil opens circuit.

Continuous coil voltage: Potential relays also have a continuous coil voltage rating. This is the maximum back EMF that the relay’s coil can tolerate continuously without overheating and opening circuit.

Dropout voltage: Potential relays also have a dropout voltage rating. This is the back EMF voltage that must be generated across the relay coil to “hold” the contacts between 1 and 2 open once they have been picked up (opened).

Note: It takes more back EMF to pick up and open the contacts (more pickup voltage) than it does to hold them open (dropout voltage). Once the cycling control opens the circuit, the rotor will decrease in speed, thus generating less back EMF across the start winding and relay coil. As the back EMF drops below the dropout voltage, the contacts between 1 and 2 return to their normally closed position and are ready for the next starting cycle.

If you’re not sure, consult with a service manual, the compressor manufacturer, or a supply house for information on selecting the correct potential relay.

Replacement relays can be cross-referenced for different manufacturers using conventional tables. For example, Steveco has cross-reference material that list two other relay manufacturers (RBM and GE), in which a cross-reference can be made for a replacement potential relay with the same specifications. (See Figure 2.) Whenever possible, the model number of the old relay should be used when ordering a new relay.

Next month’s column will cover troubleshooting the potential starting relay.

Tomczyk is a professor of HVAC at Ferris State University, Big Rapids, MI, and the author of Troubleshooting and Servicing Modern Air Conditioning & Refrigeration Systems, published by ESCO Press. To order, call 800-726-9696. Tomczyk can be reached at tomczykj@tucker-usa.com (e-mail).

Publication date: 10/07/2002

Did you enjoy this article? Click here to subscribe to The NEWS Magazine

You must login or register in order to post a comment.

error in Potential Starting Relay Voltage Specs

Rocky3247@bellsouth.net
January 6, 2011
The pickup voltage for a specified potential relay is listed as a minimum and a maximum. The actual pickup voltage must stay within this range for proper operation. THIS AN ERROR. The minimum and maximum voltages are a tolerance for the relay, actual pickup voltage needs to be above the maximum value to be sure the relay will open

Tolerance Pickup Start relays voltage

JP GEO.Pros
June 30, 2011
Q) If the to-open-operational voltage is to be above a range described in "error in specs" then why does ever the minimum of the range need to be specified, if we are to always be above the maximum of any range.. anyways

Multimedia

Videos

Image Galleries

2014 MCAA Annual Convention

Scenes from the 2014 MCAA Annual Convention in Scottsdale, Ariz.

Podcasts

NEWSmakers: Julian Scadden

Training is an ongoing process. Julian will discuss how you can generate maximum return on time and energy invested training by following a three part process. Listen to this podcast to get expert tips on training, tracking and follow up. 

More Podcasts

THE MAGAZINE

ACHRNEWS

NEWS 04-14-14 cover

2014 April 14

Check out the weekly edition of The NEWS today!

Table Of Contents Subscribe

SERVICE CALLS POLL

Which statement on service calls best applies to your business?
View Results Poll Archive

HVACR INDUSTRY STORE

plumbing-hvac.gif
2014 National Plumbing & HVAC Estimator

Every plumbing and HVAC estimator can use the cost estimates in this practical manual!

More Products

Clear Seas Research

 

Clear Seas ResearchWith access to over one million professionals and more than 60 industry-specific publications, Clear Seas Research offers relevant insights from those who know your industry best. Let us customize a market research solution that exceeds your marketing goals.

DON'T MISS A THING

Magazine image
 
Register today for complete access to ACHRNews.com. Get full access to the latest features, Extra Edition, and more.

STAY CONNECTED

facebook icontwitter iconyoutube iconLinkedIn i con