Having a specification that allows for any system option and protocol leads to a more complex system, one that is more cumbersome to install, commission, and maintain. It can be compared to allowing all employees in a company to use PCs, Macs, UNIX, and Linux computers, while also allowing Ethernet, ARCNET, and Token Ring as network communications media, and insisting that the IT department maintain and service all of these. The workload becomes unbearable, which is typically why IT departments pick one platform and stick with it.

Likewise, it is typically recommended to pick one common protocol for the entire building control system infrastructure and stick with it. The costs go down and the maintainability goes up. If there is a specific application or subsystem component that is not available on this standard protocol or if there is a specific need for using an alternate, this should be justified and a gateway (protocol translator) identified and specified. However, this should be the exception, not the norm.

Defining a common system architecture using standard, open methods is important and more appropriate than specifying the “buffet” style that allows anything to be used. An open building automation system provides interoperability where software and hardware from multiple vendors can communicate and coexist without the use of protocol converters and gateways.  There is a variety of open protocols on the market including an interoperable protocol from LonMark International. LonMark is a non-profit association made up of member companies who are manufacturers, designers, and system integrators, as well as end users committed to the development, manufacture, and use of open, interoperable products and networks.

A good open building automation system specification will define the requirements for each aspect of the system.  When defining an open spec, try to remember it is more than just the protocol that needs to be specified. There are five elements that need to be defined:

1. The Infrastructure - Including the protocol, routers, media type, IT connectivity, etc. All these should be specified based upon open standards, not on one vendor’s specific product. A single system infrastructure provides the benefits of a reduction in construction costs, lower life cycle and maintenance costs, as well as providing an improvement in performance for the whole building.

2. The Devices - These are the controllers in the network that produce, consume, or manipulate data and control/monitor the system. In an open system, it is possible to use devices from different vendors, because they all conform to a uniform industry standard, such as LON. This means that the system is not locked into a single supplier, allowing the best and most cost-effective equipment to be used. In this way, suppliers are able to concentrate on developing products, which focus on their core competency and not have to develop a complete system. Conversely, an integrator who is capable of working with the open protocol will be able to install a complete system selecting the most suitable products from different suppliers. This way, only one integrator is required for the entire system instead of multiple integrators, which can be expensive and cause isolation of the subsystems. An open system also makes upgrading easier and more flexible.

3. The Tools - These are the software or network management tools that configure, commission, and maintain the system. The tools on the system need to be able to co-exist. Device configuration plug-ins (modules) have been developed to allow use of any standard network management tool. This allows vendors to configure their devices with an open tool, meaning users are free to use tools from any vendor they choose.

4. Graphical User Interfaces - These are typically the visualization tools that the user or controls manager uses to obtain a view into the system. User interfaces allow control, monitoring, reporting, alarming, scheduling, and diagnostics. An operator workstation (user interface) affords the means to efficiently and effectively manage operations as well as display and print a graphical representation of the control network. A user interface provides the same look and feel for monitoring and control regardless of which vendor’s system or subsystem an operator is viewing. As a result, system operators need only become proficient with one user interface.

5. Enterprise Connectivity - The method for connecting the building control network into the data network - also known as the LON-LAN-WAN architecture. This ensures that the control system becomes an element of all the data sources available to the enterprise. Open interfaces have been developed to ensure data communication between the LON (the building control network) and LAN (Local Area Network) is accessible by a vendor. To provide this connectivity, enterprise level infrastructure devices are needed, and they must be specified as open. Standard routers are used which means no gateways are required.

Given this summary, it is strongly suggested to limit the main system specification to just one methodology for communication. To ensure a truly open system, all five systems elements must be open. This means each element must be interoperable and all training and servicing must be specified as open, in other words not locked into one system service provider. This, of course, is assuming there is a desire to reduce costs, improve flexibility and choice of products, provide the option for choosing the best system integrator, and allow for open bidding on both the initial installation and the long-term service contract.

For more information on open system architecture and on LonMark interoperable open systems, visit www.lonmark.org.

Publication date: 09/08/2008

Did you enjoy this article? Click here to subscribe to The NEWS Magazine

Recent Articles by Ron Bernstein

You must login or register in order to post a comment.

Multimedia

Videos

Image Galleries

2014 MCAA Annual Convention

Scenes from the 2014 MCAA Annual Convention in Scottsdale, Ariz.

Podcasts

NEWSmakers: Julian Scadden

Training is an ongoing process. Julian will discuss how you can generate maximum return on time and energy invested training by following a three part process. Listen to this podcast to get expert tips on training, tracking and follow up. 

More Podcasts

THE MAGAZINE

ACHRNEWS

NEWS 04-14-14 cover

2014 April 14

Check out the weekly edition of The NEWS today!

Table Of Contents Subscribe

SERVICE CALLS POLL

Which statement on service calls best applies to your business?
View Results Poll Archive

HVACR INDUSTRY STORE

plumbing-hvac.gif
2014 National Plumbing & HVAC Estimator

Every plumbing and HVAC estimator can use the cost estimates in this practical manual!

More Products

Clear Seas Research

 

Clear Seas ResearchWith access to over one million professionals and more than 60 industry-specific publications, Clear Seas Research offers relevant insights from those who know your industry best. Let us customize a market research solution that exceeds your marketing goals.

DON'T MISS A THING

Magazine image
 
Register today for complete access to ACHRNews.com. Get full access to the latest features, Extra Edition, and more.

STAY CONNECTED

facebook icontwitter iconyoutube iconLinkedIn i con