search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSHVAC Engineering TechnologyHVAC Engineering SectorsToday's BoilerHeating & BoilersEducational Facilities HVAC

Northeastern College Completes Boiler Upgrade

As power was not to be exported to the grid, engineers determined the optimum arrangement was to install two gas turbines from Solar Turbines, each with its own heat recovery steam generator.

By Harry Kumpula
The new chiller configuration at the college

Figure 1. The new chiller configuration at the college. Images courtesy of Rentech

July 25, 2022

A site assessment and engineering study recently indicated that the energy infrastructure of a university in the Northeast U.S. was ready for a major overhaul. Its 1.5-MW gas turbine had become a maintenance headache, and replacement parts were increasingly difficult to obtain. Additionally, the condensate return line of the steam system leaked badly, and its absorption chillers were near the end of their lives. Meanwhile, the underground electric distribution line (utility-owned) of this 250-acre campus had become a bottleneck. Almost at capacity and with college enrollment and its power load growing rapidly, only 4.16 kV was available for about three dozen buildings that added up to 2 million square feet of conditioned floor space. 

After completing a site assessment and engineering study, the university built a new combined heat and power (CHP) plant for on-site generation and upgraded its boilers. Additionally, administrators approved the installation of a central chiller plant to satisfy the school’s growing energy needs; minimize pollutant emissions; and reduce the cost of electricity, steam, and chilled water. 

Electricals and Chillers   

The upgrade began on the electrical side. In addition to a new utility 69-kV substation nearby, two 69/12.4-kV transformers owned by the college can feed 12.4 kV to its existing south substation for distribution to the campus. A further substation was built and fed by about 5 MW from two gas turbines from Solar Turbines for on-site generation. This enables the campus to continue operation in the event of a grid disturbance and operate in island mode. As part of the project, a demand-side load-reduction program helped engineers and specifiers to optimize the heating/cooling system and upgrade campus lighting. 

Figure 2. The basic configuration of the CHP featuring a Centaur 40 gas turbine from Solar Turbines and an HRSG from Rentech.

The new central chiller plant was built adjacent to an existing steam plant. It consists of two 1,000-ton electric chillers (see Figure 1) and one 2,550-ton steam turbine-driven chiller. The new equipment replaced aging absorption units in most buildings. An auxiliary chiller plant comprised of two 400-ton electric chillers serves four additional buildings. Condensate lines were replaced to eliminate leaks.

Air is served to each building at a specific temperature and humidity range. The main electric chillers are each capable of chilling about 2,000 gpm to between 42° and 54°F with an energy requirement of 0.63 kW/ton. The steam turbine-driven unit can operate at loads as low as 200 ton. It chills about 4,700 gpm to between 42° and 54° at full load and consumes 10.5 lbs./hr. of steam per ton. Two chilled-water loops operate year-round. One is 1,400 feet, and the other is 2,000 feet. Water at 45° is delivered to heat exchangers installed in most buildings. Hot water is used to regulate air temperature and humidity at the variable air volume (VAV) boxes (one per thermostat).

CHP and HRSGs 

A design assessment matched the thermal requirements of the campus to its energy load. As power was not to be exported to the grid, engineers determined the optimum arrangement was to install two solar gas turbines, each with its own heat recovery steam generator (HRSG). The Saturn 20 package from Solar Turbines (1.2 MW) came with a lube-oil system and a controls package. This single-shaft unit feeds waste heat to an HRSG from Rentech Boiler Systems. Its 150-psig steam loop operates 24/7 and serves the HVAC system, the steam-turbine-driven chiller, and the domestic hot water system.

The Centaur 40 from Solar generates up to 3.5 MW at an ISO heat rate of 12,240 Btu/kWh. When operating at full load, nearly 150,000 lbs./hr. of 820° exhaust gas flows to another Rentech HRSG, which produces nearly 20,000 lbs./hr. of steam.

Having two GTs was deemed the best option. This avoids the inefficiency associated with operating a larger machine at part load most of the time and enhances reliability. The Centaur is equipped with Solar Turbines’ SoLoNOx dry, low-emissions combustion system. Both GTs can burn natural gas and distillate. Natural gas is typically used due to state restrictions on the number of hours oil firing is allowed per year. 

Rentech HRSGs serve each machine. The boiler serving the Saturn 20 is rated 8,300 lbs./hr. at 150 psig saturated. The HRSG for the Centaur 40 produces 19,550 lbs./hr. Both units have selective catalytic reduction (SCR) units. As part of the project, a boiler from 1960 (26,000-lbs./hr.) received some maintenance upgrades to keep it in service. Two 40,000-lbs./hr. boilers from Rentech were also installed at the facility.

The biggest construction challenge was installing the new generating assets with the existing plant in service. This was accomplished by installing the Centaur 40 in the new chiller building along with its HRSG, then removing the old gas turbine and its HRSG from the original building to make room to add the Saturn 20 and HRSG. Now completed, this project provides the campus with greatly reduced energy costs. Steam and chilled water costs, too, are considerably less. It comfortably serves the growing energy needs of the university. These upgrades also helped the facility reduce emissions in keeping with state and federal regulations. 

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Harry Kumpula is the director of marketing for Rentech Boiler Systems.

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    Training and Education
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    HVAC Light Commercial Market
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    Air Source Heat Pumps
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • Case In Point

    Iowa College Boiler Upgrade Goes To The Top Of The Class

    See More
  • Craftsman Home

    Project Files: Episode 44 — Boiler Upgrade for 107-Year-Old Craftsman Home

    See More
  • Case In Point

    Hospital's Boiler Upgrade Takes a Page from the Past

    See More

Related Products

See More Products
  • Lessons Learned in a Boiler Room: A common sense approach to servicing and installing commercial boilers

  • 9781482253894.jpg

    Boiler Operator's Handbook, Second Edition

  • ghpm.png

    Gas Heating: Furnaces, Boilers, Controls, Components

See More Products

Related Directories

  • California Boiler Inc.

    For fast results and 24/7 Sales & Service, call (800) 775-2645. As a California State Licensed Contractor, California Boiler's comprehensive service approach delivers complete service throughout the life cycle of your equipment from initial planning, installation, and fabrication through ongoing training, support and maintenance. Service technicians are on call 24 hours a day.
  • Rite Boiler

    Rite manufactures and provides Low- and High-Pressure Steam Boilers, Hot Water Boilers, Blowdown Tanks, Boiler Feed System, Water Softeners, Chemical Feed Systems, and more.
  • Northeastern Supply

    Your One Stop Shop for all Residential & Commercial Plumbing, HVAC, Water System and PVF products.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing