search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSHVAC Engineering SectorsHVAC Design/Construction ProcessCommissioningCommercial HVAC

COMMISSIONING

Commissioning Action Lists: What Is Too Long?

A lengthy to-do list after FPT can cause more problems than it solves.

By Rebecca T. Ellis, P.E.
Commissioning
September 1, 2014

I am a strong proponent of planning ahead for successful functional performance testing. This is why commissioning starts in the design phase, continues through construction, and culminates (doesn’t start) with functional performance testing when the systems are installed, started up, balanced, integrated, and fully operational.

When the entire project team is engaged in a sincere and meaningful way in the commissioning planning, coordination, and integration process, we have seen testing go very smoothly and result in very few issues that need to be resolved at the end of construction. On the other hand, if the project team, or even just one or two key members of the team, do not take the commissioning planning process seriously and/or choose not to participate, the number of issues discovered during testing increases substantially.

Most commissioning professionals use some type of tabular list to document and track resolution of deficiencies with, questions about, and/or differing opinions regarding system operation. For the purposes of this column, we will call this the commissioning action list (CAL). I believe the primary goal of the design and construction phase commissioning planning and preparation is to minimize the number of items that end up on the CAL as a result of functional performance testing. An extremely long CAL is not a badge of honor or justification for the commissioning professional’s existence; it is often a symptom of the commissioning process not being as effective as it could be.

“Extremely long” is relative to the size and complexity of an individual project. However, if, on average, there are more than one to two issues per system (including all terminal units) that need to be corrected or otherwise resolved at the time of functional performance testing, that would represent a CAL that is too long.

Why are long commissioning action lists a problem?

  • It takes more time than necessary for the commissioning professional to populate the CAL.
  • Multiple project team members need to spend more time than necessary reading through and addressing the action items.
  • The commissioning professional needs to spend more time than necessary managing the CAL by tracking down responses from project team members, revising the list, and issuing updates.
  • All project team members invariably end up in multiple meetings where the CAL items are reviewed and re-reviewed until they are brought to closure.
  • The commissioning professional and responsible contractors need to retest or otherwise confirm closure of each item.

All of the above can result in the functional performance testing and system acceptance process being strung out way beyond the original project completion schedule.

In other words, an excessively long CAL will cost everyone on the project team time and money, and the building owner is often the ultimate loser. Some owners just don’t have the time, expertise, budget, or intestinal fortitude to push through an unwieldy list of issues. These owners may eventually accept the systems “as is,” because they need to close out the project and move on with their normal business activities.

Next month, this column will explore multiple reasons why the CAL might get out of hand, who might be responsible, and what the commissioning professional might do about it. 

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Rebecca is president of Questions & Solutions Engineering, Inc. She can be reached at rteesmag@qseng.com

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    Training and Education
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    News
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    Air Source Heat Pumps
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • Commissioning

    Commissioning Action Lists: Keeping Them Under Control, Part 2

    See More
  • Commissioning

    Commissioning Action Lists: Keeping Them Under Control, Part 3

    See More
  • Commissioning

    Commissioning Action Lists: Keeping Them Under Control, Part 1

    See More

Related Products

See More Products
  • new cover.jpg

    Profit is An Attitude: The Strategies You Need to Optimize Profits

See More Products

Events

View AllSubmit An Event
  • May 21, 2026

    The A2L Genie is Out of the Refrigerant Canister – What Now?

    On Demand Join this webinar to learn about key updates to refrigerant regulations. We will cover practical installation and servicing content gathered from thousands of our interactions with contractors across the US and Canada.
View AllSubmit An Event

Related Directories

  • Action Sales

    Action Sales was founded in 1994. We service the Plumbing and HVAC trades for California, Washington. Oregon, Nevada and Hawaii.
  • AABC Commissioning Group (ACG)

    The AABC Commissioning Group (ACG) is a non-profit dedicated to advancing independent commissioning professionals through education, training, and certification since 2004.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing