search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSCase in Point

Ice Thermal Storage System Saves VA Hospital Money

June 27, 2000
Just prior to the end of last year, the Veterans Administration Connecticut Healthcare System (VACHS) completed a campus rehab project that has earned several energy-related awards and is due to earn more. Innovative lighting and chiller plant rehabs, plus new controls, a plate-and-frame heat exchanger, and an ice thermal storage system are saving this facility an average of $700,424 per year in operating costs. In compliance with the Energy Policy Act of 1992 and Executive Order 12902 to reduce energy consumption in federal buildings by 30% by the year 2005, the Department of Veterans Affairs sought to identify ways to reduce its operating costs and improve the facilities’ atmosphere for both employees and patients. It also wanted to take advantage of utility rebate monies offered by Southern Connecticut Gas and United Illuminating Company, and it needed to identify ways to finance the building improvements. VACHS is a complex of 28 buildings (including two, 12 story high-rise structures) spread out over 42 acres. Its space includes 1,125,000 sq ft, 1,200 people, 350 beds, plus specialty care, and blind rehabilitation centers. The complex dates back to the 1920s, and the high-rise buildings were constructed in the early 1950s. A central chilled water system was installed in 1964.



Contracting for Energy Savings

Robert A. Palazzi, chief, design and development for the VACHS, was selected to act as energy manager for the project. He sought the expertise of several energy service companies (ESCOs), reviewed proposals, and selected EUA Cogenex (Lowell, MA) based on the company’s ability to meet the VA’s needs and provide guidance concerning finances and energy service contracts. Working with Cogenex, Palazzi implemented the first Energy Savings Performance Contract (ESPC) within the VA system.

The project was completed in two phases. Phase One replaced approximately 8,000 incandescent and fluorescent fixtures with modern, energy efficient fixtures. Two inefficient 885-ton centrifugal chillers were replaced with a 1,000 ton, two-stage, new steam absorption chiller and a new 800-ton electric centrifugal chiller, both by York International (York, PA). The aging cooling tower, chilled water, and condenser water pumps were all replaced with new equipment and energy efficient motors. Bell & Gossett (Morton Grove, IL) provided the base-mounted centrifugal pumps.

A ddc control system, the Infinity SCX 920, by Andover Controls (Andover, MA) was installed to control the new chiller plant. Square D (Palatine, Il) provided the electrical distribution control center. By implementing Phase One, VACHS pioneered performance contracting for energy services in the VA system.

Phase Two expanded the plant capacity with a 6,600 ton/hr ice thermal storage system by Baltimore Aircoil Company (Baltimore), the TSU 60MAP, and converted the chilled water pumping system to a primary/secondary loop operation. This expansion provided the necessary cooling capacity for the addition to the clinic, which added 100,000 sq ft to this facility. The ice storage system is driven by screw machines that operate at night, during off-peak electric utility periods, to provide the 20˚F fluid necessary to make the ice. The stored ice is then used during the on peak electric utility period, requiring only the electrical power necessary to move the fluid to the heat exchangers. APV Heat Exchangers Inc. (West Sussex, England) provided the plate-and frame-exchanger.

Both ice thermal storage and conventional cooling systems were evaluated for Phase Two, and ice storage (without consideration for energy rebates) proved to be the lower first cost alternative. According to Stuart Erhardt, Senior Project Manager of Cogenex, “Ice thermal storage and night time chiller operation at lower wet bulb temperatures met capacity requirements with existing equipment. This enabled the VA to avoid the capital investment for additional cooling towers that would have been required with a conventional system. With the added benefit of energy rebates, there was no question that ice was the way to go.

Diversified Technology Consultants (North Haven, CT) acted as the design-build consultant, and Mulvaney Mechanical Inc. (Ridgefield, CT) was the mechanical contractor for the project.



Success on Many Levels

The project earned rebates from United Illuminating Company totaling $310,966 for lighting and high efficiency motors and $100,000 from Southern Connecticut Gas for the installation of the absorption chiller.

An additional $294,520 rebate was received from the United Illuminating Company for the ice thermal storage system. The actual savings for the project add up from each part of the project: $285,000 from the chiller plant, $185,000 from the lighting, and $130,000 from the ice thermal storage system.

The hospital saved on electrical costs as well. Chiller plant kilowatt usage went from 2,580,134 to 16,680; the new lighting systems’ electrical usage went from 2,470,800 to 8,276; and the ice thermal storage uses a mere 7,222 kW.

According to Mr. Palazzi, “The ESPC that has been initiated at VA Connecticut Healthcare System, West Haven campus has exceeded our original expectations.”

Intangibles factor into the savings as well. The new chiller plant is saving energy and experiencing reduced maintenance and repair costs; the system conserves nonrenewable fuels achieving environmental fuels and energy cost reduction goals identified in the Energy Policy Act of 1992; The ice thermal storage system saved $650,000 in first cost, and is saving $100,424 annually in operating costs.

To date, the VA Connecticut Healthcare System project has earned several awards and acknowledgements, such as the Federal Energy Management Team Award for Energy Savings Performance Contract, the Energy Champion Award by DOE for the “You Have The Power Campaign,” and the Total Rehab Award given by Energy User News (an Engineered Systems sister publication).

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    Training and Education
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    HVAC Residential Market
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    Air Source Heat Pumps
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • The Benefits of Ice Thermal Storage

    See More
  • Thermal storage system offers comfort plus savings

    See More
  • IndustryNews

    Ice Energy thermal storage project to help California residents save energy

    See More

Related Products

See More Products
  • Training-System-2017.jpg

    Customer Service Training System by Steve Coscia

  • Training-Managing-System-2017.jpg

    Customer Service Training & Managing System by Steve Coscia

  • srepm.png

    System Recovery & Evacuation

See More Products

Events

View AllSubmit An Event
  • November 12, 2025

    A2L in Action: Proven Performance in Cold Storage

    On Demand This webinar will provide insights into the process, challenges, and successes of implementing this new A2L technology, showcasing how industry leaders are paving the way for a more efficient and environmentally friendly future.
View AllSubmit An Event

Related Directories

  • Chester-Jensen Co. Inc.

    Refrigeration evaporators, water chillers, thermal storage equipment, ice builders.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing