search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSHVAC Engineering SectorsData Center HVAC

16 Observations to Consider for Live Multitenant or Enterprise Data Center Infrastructure Upgrades

By Saahil Tumber, P.E. LEED AP, HBDP
Interviews

Detailed interviews between the owner’s stakeholders and the design and construction team are recommended to align expectations through a more thorough understanding of current and future needs, planned initiatives, and interdependencies.

October 19, 2020

Data centers are expected to operate 24/7/365. When critical infrastructure reaches the end of its useful life, data centers become prone to unplanned outages, and equipment replacement becomes critical. There are also instances where upgrades are necessary to increase capacity, consolidate loads, and remediate points of failure. There is also the potential to capture stranded capacity and space and maximize the ability to support IT loads.

While each project involving infrastructure upgrades is different and has its unique set of requirements and challenges, here are 16 ideas to consider during the programming and planning phase for multitenant and enterprise data center infrastructure upgrades.

1) Review the owner’s project requirements (OPR). The OPR should clearly define the overall objectives, goals, and expectations of the project. Detailed interviews between the owner’s stakeholders and the design and construction team are recommended to align expectations through a more thorough understanding of current and future needs, planned initiatives, and interdependencies.

2) Owners can gain valuable insight through validation of their power and cooling requirements. The building management system (BMS) and electrical power monitoring software (EPMS) trend logs, electricity bills, equipment readouts, and more can provide useful information. The past and current usage can be coupled with planned initiatives and deployment models to forecast future requirements.

3) Based on forecasting results, owners can establish milestones where additional capacity needs to be deployed or equipment needs to be replaced to meet project objectives.

4) Engage engineers to identify any major constraints that could pose a challenge to the infrastructure upgrade project through conducting a gap analysis.

5) If the facility has an original master plan that addressed expansion or densification as part of a future phase, review the plan and confirm it is still valid.

6) Review available documentation to get an in-depth understanding of the data center systems. Survey the data center in detail and conduct interviews with the data center’s operators. If there have been outages in the past or there are recurring issues, it is critical that the root cause be identified.

7) For multitenant and enterprise data center owners requiring concurrent maintainability or fault tolerance, identify any points of failure that can impact the data center and review remedial options with the stakeholders.

8) Verify the effectiveness of the data center cooling system if the project scope involves related upgrades. The available cooling capacity cannot be fully utilized if there are deficiencies. Consider a computational fluid dynamics (CFD) analysis to validate the existing conditions and provide recommendations for increasing the effectiveness.

9) Occasionally, there are circumstances that impact the entirety or certain elements of the upgrade project, such as pending mergers and acquisitions, litigation, security requirements, government regulations, or other issues. Adjustments to stakeholder expectations and requirements may be needed.

10) For multitenant data centers, review the impact of upgrades and construction activity on agreements — e.g., service level agreements (SLAs), lease, etc. — between the customer and the provider. There are implications if the agreements are violated, and the potential impact should be reviewed.

11) Review the financial impact of the upgrade project. Utility companies frequently offer incentives if upgrades will lead to reduction in energy usage (kWh) or peak power (kW), and the incentives can partially offset the project cost.

12) For projects that involve an increase in capacity or density, expanding the existing systems and deploying existing technologies already on-site might not be appropriate in certain situations. Review options and alternates that best meet the data center owner’s project objectives. Criteria such as space requirements, structural implications, financial impact (CapEx, OpEx, TCO), potential risks, reliability, time-to-market, commissioning challenges, code impact, and much more need to be considered.

13) Consider involving a preconstruction team (general contractor and subcontractors) to help with pricing, logistical support, construction feasibility, equipment procurement, construction scheduling, development of methods of procedures (MOPs) and standard operating procedures (SOPs), creating safety protocols, and more during the planning phase.

14) The upgrade project also offers an excellent opportunity for the data center facility and operations team to provide input and gain hands-on experience as MOPs/SOPs are developed and implemented in preparation of construction. Their participation during the entire planning phase is highly recommended.

15) It is important for the commissioning agent to be involved during the planning phase. Commissioning systems in a live data center has its own set of challenges, and the commissioning agent needs to develop strategies and provide input to the design team.  

16) Construction activity can be intrusive, and there are risks associated with working in a live data center. The risks can be minimized with detailed planning but can never be eliminated. Murphy’s Law can render even the best plan and strategy ineffective. Consider creating contingency plans and fallback options in collaboration with the stakeholders to help mitigate the risks.

By following the thought process and underlying philosophy shared above, upgrades to a live multitenant or enterprise data center can be implemented in a successful manner with little or no impact to its operations.

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Saahil tumber

Saahil Tumber, P.E. LEED AP, HBDP, is a technical authority at Environmental System Design Inc. His engineering mindset serves him best in finding innovative solutions to complex problems. He strives to work closely with the client and end users as their trusted advisor and to develop fit-for-purpose solutions that best meet their objectives. He facilitates collaboration, coordination, and communication between the stakeholders to drive the project towards success. Saahil does not believe in the cookie-cutter design approach — he considers each project unique and deserving of a tailored solution and prefers to anticipate challenges, but should a challenge unexpectedly arise, he acts on it in a timely manner, discusses it with necessary parties, and analyzes all options to develop the solution that best serves the needs of the project.

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    Training and Education
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    HVAC Contracting
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    Air Source Heat Pumps
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • Tesla Gigafactory

    How Data Center, Infrastructure Construction is Making Up for Delays in EV Plant Construction

    See More
  • Infrastructure Upgrades At Live Data Centers

    Infrastructure Upgrades At Live Data Centers

    See More
  • Static Pressure Measurement Device.

    Time to Consider Pascals for Static Pressure Measurements

    See More

Related Products

See More Products
  • The ACHR News - February 16, 2026

    ACHR NEWS February 16, 2026, Issue

  • The ACHR News - June 16, 2025

    ACHR NEWS June 16, 2025, Issue

  • The ACHR NEWS - March 16, 2026

    ACHR NEWS March 16, 2026, Issue

See More Products

Events

View AllSubmit An Event
  • June 24, 2025

    Regional Considerations in Data Center MEP Design: From Desert to Coast

    On Demand Join ES NEWS' Editor Austin Keating and the panel for an expert examination of regional data center design strategies. They will be joined by data center commissioning experts and manufacturer representatives.
  • March 11, 2026

    Insulating the Cloud: Insulation Solutions for Data Center Demands

    On Demand Gain practical insights into material selection, efficiency optimization, and real‑world challenges faced in fast‑growing data‑center environments. Join us to elevate your understanding of high‑performance mechanical insulation strategies.
View AllSubmit An Event

Related Directories

  • A to Z Sales & Marketing

    We strive to revolutionize indoor living through innovative solutions that improve air quality, enhance comfort, and promote sustainable living for people around the world.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing