search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSHVAC Engineering TechnologyHVAC Engineering SectorsVentilation and IAQCooling & ChillersData Center HVAC

Pharmaceutical Cooling Tower Replacment Design-Build Project

By Amanda Parolise
Facility Files
November 5, 2017

This month’s Facility File will focus on the B2B November test for HVAC applications to replace an existing cooling tower at a pharmaceutical facility. The project delivery method is design-build (D-B) with a guaranteed turnkey cost. The D-B firm will assign a project manager with pharmaceutical and infection control (IC) background to the project. The D-B firm has in-house engineering, technicians, estimator staff to be involved in the design and cost estimate the initial design phase. The scope of work will be a basis of design to meeting the owner’s need to replace this antiquated unit with a 150-ton, modular blow-through cooling tower to serve the existing closed loop condenser water system. 

Prior to the D-B team’s concept document submission, the facility manager and his O&M staff will want to contribute information to the D-B team’s writing of the contract specification/basis of design document and, more specifically, to the following activities: service contracts, parts inventory, and as-built drawings requirements. Reviewing the design phase documents, this O&M staff will want to be assured that equipment serviceability is adequate and safe (e.g., equipment located on the roof, Legionnaire’s concerns).

At the recommendation of the D-B team leader, the HVAC engineer, and the O&M staff will review ASHRAE 2015 — HVAC Applications Handbook, chapter 58 (Integrated Building Design), to get a better understanding of how design-build is a team effort. In addition, the D-B and owner’s team are directed to 2016 ASHRAE Handbook – HVAC Systems and Equipment, and more specifically, chapters 1 (HVAC System Analysis and Selection) to select the optimum cooling tower, chapter 14 (Condenser Water Systems), and chapter 40 (Cooling Towers). It is also recommended that the design team and the owner’s team review the Cooling Technology Institute (CTI) cooling tower manual and the CTI certification.

A D-B team meeting will be coordinated so that the owner representative, 3rd-party IC consultant, 3rd-party commissioning and TAB consultant, and the O&M manager review together chapters 36 through 46 of the ASHRAE handbook concerning building operations and management. This information combined with the owner’s own knowledge of operating the condenser water systems and the facility’s infection control department will assist the D-B team in understanding the intricacies of owning, operating, and managing this building.

The D-B team will also deliver the specific collection of equipment documents in a manner such that the O&M computer operator can input the data collection into the CMMS system so that the existing preventive maintenance (PM) program will be workorder ready for day one of cooling tower operation.

In the startup and pre-commissioning phases, the O&M staff will be proactive in following along with the D-B’s trade technicians to receive equipment, system, and ATC tablet computer training using the O&M manuals and design phase documents (that will eventually become the as-built drawings).  

Once the startup has been completed, the ATC subcontractor and owner representative/ 3rd-party CxTAB consultant will complete the functional performance testing of the new cooling tower renovation and the associated condenser water pipe distribution and associated balancing work. The D-B team shall go through an automatic control system initial dry-run demonstration prior to the D-B firm, demonstrating the system to the CxTAB consultant. The 3rd-party infection control commissioning consultant shall complete her close-out of process, including updating the IC policy and procedure document for working at the tower.

 

The ATC subcontractor will begin collecting condenser water system data and performance by trending the localized monitoring via computer data collection of the following:

[X] outdoor dry bulb and wet bulb temperature  [X] condenser water supply and return temperature  [X] tower water make-up [X] condenser pump performance [X] cooling tower and fan performance [X] HVAC alarms  [X] safety alarms

 

Taking the same approach as the owner representative and design engineers, the pharmaceutical O&M personnel will use a series of computer-generated touchscreen project checklists that allows the staff to confirm that the following facility data has been collected. This process should start at the beginning of construction/build phase and not at project closeout, so that the facility files can be inputted into the CMMS system. Touchscreen O&M checklists should include:

[X] equipment shop drawings [X] O&M manuals, parts list, and lubricants [X] troubleshooting tips [X] tower startup and shutdown instructions

 

The training process should include specific HVAC and ATC system and equipment training but also IC policy and procedure plan training. Training should also include the preventive maintenance work order system to routinely assure continuous tower and condenser water supply performance. This will require the D-B firm to provide the associated system flow diagrams noting set points versus actual and adjustments as part of the project closeout documents. Touchscreen training checklists should include:

[X] equipment [X] system [X] emergency plan [X] automatic controls [X] infection control management

 

To read the article in pdf form, please see here.

More Facility Files here. 

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Parolise is project manager consultant with BuildingSmart Software LLC. Reach her at mckew@yahoo.com.

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    Training and Education
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    HVAC Light Commercial Market
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    News
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • Design bid build

    New Cooling Tower for a Pharmaceutical HVAC Replacement Using Design-Bid-Build Project Delivery

    See More
  • Back 2 Basics image

    Critical HVAC Data Center Cooling Tower Replacement Design-Bid-Build Project

    See More
  • Facility Files

    Maintaining Construction Space Negative Pressure (Design-Build Project)

    See More

Related Products

See More Products
  • Manual LLH Cover_Final.jpg

    Manual LLH - 2019 (HVAC System Design for Low Load Homes)

  • 9781439842126.jpg

    Heat Exchanger Design Handbook, Second Edition

  • Manual_SPS_new.jpg

    Manual SPS HVAC Design for Swimming Pools and Spas [ANSI/ACCA 10 Manual SPS - 2010 (RA 2017)]

See More Products

Related Directories

  • Rakshan Cooling Towers

    Rakshan Cooling Towers is a leading manufacturer in India, delivering energy-efficient, durable, and customized cooling tower solutions for industrial, commercial, and HVAC applications.
  • World Cooling Towers

    World CoolingTowers is a leading cooling tower manufacturer in India. We manufacture and Supply highly durable cooling towers at a reasonable price.
  • REYMSA Cooling Towers

    REYMSA Cooling Towers has been in the cooling tower business for more than 55 years and offers the best Non-Corrosive Cooling Tower on the market.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing