search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSHVAC Engineering TechnologyHVAC Engineering SectorsHVAC RetrofitsHeating & BoilersEducational Facilities HVAC

Temporary Air Conditioning For An Emergency Shelter Center -- Infrastructure Project Delivery

By Amanda Parolise
Facility Files
April 8, 2017

This month’s Facility File will focus on the B2B April test for an HVAC application within a high school facility, with the existing field house HVAC system being retrofitted to serve as an emergency shelter building with its associated locker rooms and toilet facilities.

It is not uncommon for a school building to also serve as a safe place during a crisis such as a tornado or hurricane. It would be very beneficial for the school department and town/school building department, along with the rest of the IPD (integrated project delivery) team, to read the FEMA Risk Management Series Design Guidance for Shelters and Safe Rooms (May 2006) pertaining to design guidelines for shelters for people. The town/school facility group should also read the 2015 ASHRAE Handbook Applications chapters 36 through 43, addressing building operations and management to assist in preparing for the temporary addition of chilled water cooling. This information combined with the school’s own knowledge of operating the existing field house four central AHUs will help the IPD team in understanding intricacies of operation when the temporary HVAC rental equipment arrives on site

With the FEMA and ASHRAE design guidelines, the IPD team (consisting of town/building owner, owner representative/commissioning and air and water balancing consultant, HVAC consultant engineer, electrical and plumbing sub-consultants, general contractor and HVAC and electrical sub-contractors, as well as the temporary HVAC rental equipment contractor) should meet with the school’s operations personnel to discuss specific building standards that need to be applied to this project. For this project, the facility operation is handled by an in-house staff, but the operation and maintenance of the rental equipment will be executed by the rental equipment company, beginning with air-cooled chiller hook-up, operation, shutdown, and removal. The design team’s contract drawings and specification requirements will include O&M, training, and energy operating budget impact.

In the Concept Development of the IPD project, the town/school building department and operation personnel will want to contribute information to the design team member’s writing of the contract specification and more specifically the following activities: rental contract, response time criteria, assemble and disassembling of this equipment, service contracts including parts and material, and temporary tie-in as-built drawings requirements. Reviewing the design documents, this O&M staff will want to be assured that equipment serviceability is adequate and safe and the neighborhood sound levels will be acceptable to the town’s building department.

The project delivery method is integrated project delivery (IPD) working together with owner-designer-builder based on a building program construction budget, so the general contractor and his/her in-house engineering and estimator (along with the prime subcontractors) will be involved in the design phase and be able to contribute to the contract documents. In the construction phase, the O&M staff and the HVAC rental equipment contractor will want to revisit the issues noted earlier during the design phase. Next comes the startup and commissioning phases, and the rental company will want to be proactive in following along with the IPD team’s mechanical-electrical in-house coordinator to observe installation assemble and disassembling training from the HVAC equipment rental technician. ES

 

Once the startup has been completed, the school’s ATC technician and owner representative/3rd-party commissioning and TAB consul-tant will complete a dry-run chilled water emergency system test run, working closely with the HVAC rental equipment technician prior to commissioning this special system mode of operation. The school’s ATC technician, along with the rented air-cool chiller and electrical generator technician, will begin collecting field house emergency shelter system performance by trending pertinent HVAC system and equipment data of the rooms involved, the four central AHUs, and the rental equipment as follows:

[X] room dry bulb and wet bulb temperature [X] supply air and return air dry bulb and wet bulb temperatures [X] chilled water supply and return temperature [X] outdoor air dry bulb and wet bulb temperature [X] packaged chiller control points and trending data [X] packaged electric generator control points and trending data [X] alarms [X] offsite rental equipment contractor’s interface.

The O&M staff should review the contractor-produced piping field fabrication/field coordination drawings prior to fabrication. The design team’s installation service drawing checklists should include:

[X] location of shutoff valves, ATC valves, and balancing valves [X] strainers [X] equipment and control devices changeover steps.

The training process should include specific HVAC system and equipment training but also emergency and security plan. The design engineer’s chilled water piping calculations associated with this field house area piping zone should be updated after the final TAB report. This will require the TAB subcontractor to provide the water balancing reports along with the associated system flow diagrams, noting quantities and pressures for future rebalancing if necessary, as part of the project closeout documents. A checklist of piping system documentation should include:

[X] equipment connections [X] chilled water piping system [X] emergency plan [X] automatic controls [X] air-handling sequence of operation under emergency shelter conditions.

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Parolise is project manager consultant with BuildingSmart Software LLC. Reach her at mckew@yahoo.com.

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    News
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    HVAC Light Commercial Market
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    HVAC Residential Market
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • Facility Files

    Air Conditioning For A Datacom Room Expansion Using Integrated Project Delivery

    See More
  • Back 2 Basics image

    Air Conditioning For A Datacom Room Expansion Using Integrated Project Delivery

    See More
  • Back 2 Basics image

    Temporary Air Conditioning Using Owner In-House Project Management

    See More

Related Products

See More Products
  • EHEP002028.jpg

    Principles of Heating, Ventilation, and Air Conditioning in Buildings, 1st Edition

  • ac.png

    Air Conditioning Service Guide R-410A and R-22 Systems 2nd Edition

See More Products

Related Directories

  • Ai Air Conditioning Corp.

    AI Air Conditioning Corp. is a New York-based wholesaler and distributor of Midea heating, ventilation, and air conditioning (HVAC) systems, offering products and engineering support for commercial and residential projects.
  • International Training Institute for the Sheet Metal and Air Conditioning Industry-ITI

    ITI supports sheet metal union apprenticeship and advanced career training by developing and producing standardized sheet metal curriculum for union members.
  • Sheet Metal & Air Conditioning Contractors' National Assn.-SMACNA

    SMACNA is an international trade association that promotes excellence in the sheet metal and HVAC industry. SMACNA develops technical standards for the industry, including the popular Architectural Sheet Metal Manual. Visit the SMACNA online store at https://store.smacna.org for our standards.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing