search
Ask ACHR NEWS AI
cart
facebook twitter instagram linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
  • NEWS
  • TECHNOLOGY
    • Heating & Boilers
    • Cooling & Chillers
    • Pumps & Flow Controls
  • SECTORS
    • Commercial
    • Health Care
    • Data Center
    • Educational Facilities
  • DESIGN | CONSTRUCTION
  • OTHER TOPICS
    • High-Performance Buildings & Automation
    • Ventilation and IAQ
    • Commissioning
    • HVAC Retrofits
  • TODAY’S BOILER
    • Today’s Boiler Archives
    • Today’s Boiler Digital Edition
  • MORE
    • Case Studies
    • Podcasts
    • Videos
    • Directory
    • Webinars
    • ES NEWS Store
    • White Papers
  • SIGN UP
  • Back to The NEWS
Engineered Systems NEWSHVAC Engineering SectorsHVAC Design/Construction ProcessCommissioningCommercial HVAC

COMMISSIONING

Post-Commissioning Design Changes

Don’t let project modifications alter your commissioning goals.

By Rebecca T. Ellis, P.E.
Commissioning
February 2, 2015

The commissioning process is intended to follow a logical flow in a logical project delivery process. It assumes that the owner’s project requirements (OPR) are translated into design documents, which are implemented by the contractors and verified to achieve the OPR by the commissioning professional. Documentation and training  are then developed for the owner and delivered to the O&M staff to set the stage for continued proper operation of the new systems.

Ideally, the process follows a straight path forward, but in reality, there are periodic detours, reversals, and rework that affect the commissioning process. These lead to extra effort for everyone on a project team, including the commissioning professional. As with most elements of a design and construction project, the later such changes occur, the more disruptive and costly they are to the commissioning process and deliverables.

One of the worst-case examples is when design changes are made to a system by the design team after functional performance testing of that system. This is sometimes because the system in question is unable to achieve its OPR performance criteria even though the system performed as originally designed and documented in the construction contract. In a few cases, a perfectly fine system needs to change in order to accommodate modifications made to another system that did not pass its commissioning tests. In other cases, the owner realizes that the original OPR criteria are not really acceptable.

The purpose of this month’s column is not to dwell on the causes of the late-in-the-game design changes, but I list a few possibilities here.

  • The owner changed the OPR.

  • The design team disregarded previous commissioning design review comments.

  • The design and/or construction team disregarded previous commissioning submittal review comments.

  • The root cause of the system’s inability to achieve the OPR was so unique, complex, or subtle that no one on the project team identified it ahead of time.

The purpose of this column is to outline the additional effort required by the commissioning professional in order for the commissioning process not to be derailed and/or compromised by significant design modifications after functional performance testing. Some of this commissioning rework is associated with verifying that the systems perform according to the new design and/or OPR, and the other rework is associated with modifying the systems documentation and training to ensure that the O&M staff receive the most up-to-date and accurate information.

Systems Operation Verification

  1. Modify customized functional performance test procedures to reflect the new design. This typically includes revised test steps and new acceptance criteria.
  2. Retest each affected system to confirm new design performance is achieved without negatively affecting unchanged system elements or systems integration.
  3. Document any deficiencies discovered during new testing.
  4. Track resolution of any new deficiencies.
  5. Retest to confirm successful resolution of any new deficiencies.

O&M Documentation & Training

  1. Revise systems manual to reflect design changes. This may include OPR documentation, basis of design documentation, sequences of operation, schematic diagrams, systems integration descriptions, preventive maintenance schedule, and recommissioning test procedures.
  2. Conduct a supplemental training session to explain design modifications, any related operational strategy changes, and the reasoning behind them.

In conclusion, I offer a couple words of advice. For commissioning professionals — do not give up and do not let schedule pressures force you to compromise the results of the commissioning process after coming so far. For owners — do not be surprised if commissioning costs increase if the design changes after construction is complete. 

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

 

Rebecca is president of Questions & Solutions Engineering, Inc. She can be reached at rteesmag@qseng.com

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • HVAC-enrollment

    The Trades Are Back: HVACR Programs See Nearly 30% Enrollment Spike

    A new wave of future technicians is entering the pipeline.  
    Training and Education
    By: Matt Jachman
  • 2025 Top 40 Under 40

    2025 Top 40 Under 40 HVACR Professionals List

    The 11th annual Top 40 Under 40 list highlights those...
    HVAC Contracting
    By: Hannah Belloli-Oster
  • LG Ductless Mini-Split Systems

    The 9 Types of Heat Pumps

    As the U.S. moves toward electrification, heat pumps are...
    HVAC Residential Market
    By: Joanna R. Turpin

More Videos

Today's Boiler

Spring 2026 Issue

Today's Boiler - Spring 2026 Cover

Read More from Today's Boiler

Case in Point Logo

Smarter Hydronic Design for Data Centers - Free Webinar - January 22, 2026

Related Articles

  • Commissioning

    Testing-Phase Design Changes

    See More
  • Water Heater Design Changes In The Works

    See More
  • IDV-ACHR-News

    Seven Design Changes That Reduce Refrigerant Charge

    See More

Related Products

See More Products
  • Manual_SPS_new.jpg

    Manual SPS HVAC Design for Swimming Pools and Spas [ANSI/ACCA 10 Manual SPS - 2010 (RA 2017)]

  • DUCT DESIGN.gif

    HVAC Systems Duct Design

  • 9781439842126.jpg

    Heat Exchanger Design Handbook, Second Edition

See More Products

Related Directories

  • AABC Commissioning Group (ACG)

    The AABC Commissioning Group (ACG) is a non-profit dedicated to advancing independent commissioning professionals through education, training, and certification since 2004.
  • Design Polymerics

    Design Polymerics manufactures low VOC, LEED qualified, duct sealants, duct liner adhesives and insulation mastics. We now offer silicones and MS polymer sealants.
×

Sign Up. Stay Informed.

The #1 trusted source for the HVACR industry since 1926

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Advisory Board
    • Classifieds
    • Submit a Letter
    • Directories
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing