LAS VEGAS, NV — If the new Suncoast Hotel & Casino had been built anywhere else but here, it would have been a three-year job. Not so in Sin City.
“We had to complete it in 14 months,” says Jack Arnold, MEP coordinator for general contractor J.A. Tiberti Construction Co., Inc. “Always in Vegas it’s the demand for the short time frame. I’m always dealing with very strict time constraints.”